72
TEST PROCEDURES
If there is no CC-16 or CC64 controller
connected, connect it now. You will also
need the power supply for the controller.
Click on the Properties view
.
Check Firmware Version on properties
dialog box. Select ESP 1 view.
This setup is a straight-through connection
for this test. Click the connect icon.
When the connection is completed, the
background color will change.
Click the connect icon again. At this point
the ESP is settled to the proper configuration
for this test.
After disconnect, the ESP-88 chassis must
be powered off and powered on again.
This power off sequence is needed by the
time test. It is recommended to use same
PC that set this configuration and to run the
ATS2 macro that will be described later.
This will avoid the time difference between
the two PC’s.