Replacement Procedures
8-72 Vivid E80/E90/E95 – Service Manual
GC091052
Rev. 3
3. Remove the Main Cable, including the Cable Chain away
from the Ultrasound system.
Install the Main Cable
Follow this procedure to install the Main Cable:
1. Route the Main Cable, including the Cable Chain into its
position.
2. Install the two (2x) screws used to attach the Cable Chain to
the UI.
3. Install the screw at the other end of the Cable Chain.
4. Connect the D-SUB to J21 on the BEP I/O.
5. Connect the DVI to J22 on the BEP I/O.
6. Connect two (2x) cables to the XYZ Control box.
7. Route and connect the two XY cables.
8. Connect the HDMI connector to the Bulkhead.
9. Install the Cable Clamps.
10. Connect the cable to the Z-switch.
11. Power up the Ultrasound system.
12. Verify that the XYZ functions operate as they should.
13. Power down the Ultrasound system.
14. Install all covers.