GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL
118
At last, engineering commissioning is completed when " " is displayed on "Project Debug
Completion".
Note:
During commissioning, users must listen to the operating sound of outdoor and indoor fans
and compressors to check for exceptions.
3.3.3.2.3 Commissioning Through the Portable Commissioning Tool
Step 1: Connect the Portable Commissioning Tool. Please refer to the operation manual of Portable
Commissioning Tool for the connection method.
Step 2: Setting DIP of ODU address. You must set this DIP in main control ODU. The setting code
(SA8) of main control unit shall be set to 00. Otherwise, it is invalid.
Step 3: On the home page, press Unit Debug to enter into the page of engineering debugging.

Table of Contents

Other manuals for Gree GMV-280WM/E-X

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GMV-280WM/E-X and is the answer not in the manual?

Gree GMV-280WM/E-X Specifications

General IconGeneral
BrandGree
ModelGMV-280WM/E-X
CategoryAir Conditioner
LanguageEnglish

Related product manuals