TESTRUN/AIRPURGE
COMMISSIONING
! CAUTION
It is recommended start the unit (rst power ON) with heater forced OFF and compressor forced
OFF (See “6.3 Seng of DIP switches and RSW switches”). In order to circulate water by water
pump and remove possible air into the heater (Check heater completely lled).
8.4 Test run / air purge
Test run is a working mode used when commissioning the installaon. Some sengs are made to
let the installer an easy job. Air purge funcon drives the pump in a way for evacuang air bubbles
in the installaon.
Example for PC-ARFH2E
This menu shows the following test to be launched:
• Unit Test Run
• Air Purge
• Screed Drying
• Pump down procedure
Aer “Test Run”, “Air Purge” or “Pump down procedure” opon is selected, the YUTAKI user
controller asks for the duraon of the test.