EasyManuals Logo
Home>Lennox>Chiller>MCC Series

Lennox MCC Series User Manual

Lennox MCC Series
98 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #17 background imageLoading...
Page #17 background image
Installation - Operation - Maintenance manual (IOM) AIR COOLED CHILLERS & SPLIT UNITS - 0105-E • 15 •
Minimum refrigeration capacity in kW for oil entrainments up Suction risers
Refrigerant : R407C
Table C Tubing nominal OD, mm
Saturated Suction gas
temperature (°C) temperature (°C) 12 15 18 22 28 35 42 54 67 79 105 130
-5 0 0,39 0,71 1,20 2,04 3,88 6,88 11,11 21,31 36,85 55,86 115,24 199,30
10 0,37 0,68 1,14 1,94 3,68 6,53 10,54 20,20 34,94 52,95 109,25 189,14
5100,47 0,86 1,45 2,47 4,69 8,33 13,44 25,77 44,58 67,56 139,39 241,30
20 0,44 0,81 1,36 2,31 4,39 7,79 12,58 24,13 41,73 63,25 130,49 225,90
Minimum refrigeration capacity in kW for oil entrainments up HOT-Gas risers
Refrigerant : R407C
Table D Tubing nominal OD, mm
Saturated Discharge
discharge gas
temperature (°C) temperature (°C) 12 15 18 22 28 35 42 54 67 79 105 130
30 70 0,60 1,09 1,84 3,13 5,95 10,55 17,03 32,65 56,47 85,59 176,59 305,70
80 0,58 1,06 1,79 3,04 5,78 10,25 16,55 31,74 54,90 83,21 171,67 297,19
90 0,57 1,04 1,74 2,96 5,64 10,00 16,14 30,95 53,53 81,13 167,39 289,77
40 80 0,62 1,13 1,90 3,24 6,16 10,93 17,65 33,85 58,55 88,73 183,07 316,92
90 0,60 1,10 1,85 3,16 6,00 10,65 17,19 32,96 47,01 86,40 178,26 308,60
100 0,58 1,07 1,80 3,07 5,83 10,34 16,70 32,02 55,38 83,94 173,17 299,79
50 90 0,63 1,16 1,94 3,31 6,29 11,16 18,02 34,55 59,77 90,58 186,88 323,52
100 0,61 1,12 1,88 3,21 6,10 10,82 17,47 33,50 57,95 87,83 181,21 313,70
110 0,60 1,09 1,83 3,13 5,94 10,54 17,02 32,63 56,44 85,53 176,47 305,49
3.7.3 - Mechanical isolation of refrigerant lines
Isolate refrigerant lines from the building to prevent the vibrations normally generated by the lines to the building
structure. Avoid bypassing the isolation system on the unit by fixing refrigerant lines or electrical conduits too tightly.
Any vibrations will be transmitted to the building by rigid piping.
Lack of vibration isolation on refrigerant pipework will lead to early failure of copper pipe and loss of gas.
3.7.4 - Pressure test
To avoid formation of copper oxide during brazing operations, blow a little dry nitrogen through the pipes.
Piping must be made with tubing that is perfectly clean, plugged during storage and between connections
operations.
During these operations, observe the following precautions:
1) Do not work in a confined atmosphere, refrigerant fluid can cause asphyxiation. Make sure there is sufficient
ventilation.
2) Do not use oxygen or acetylene instead of refrigerant fluid and nitrogen for leak testing : this could cause a violent
explosion.
3) Always use a regulator valve, isolating valves and a pressure gauge to control test pressure in the system.
Excessive pressure can cause lines to burst damage to the unit and/or cause an explosion with severe personal
injury.
Ensure conduct liquid line and gas line pressure tests are in conformity with applicable legislation. Before starting
up a unit on a receiver, the piping and the condenser must be dehydrated. Dehydration should be carried out using
a double stage vacuum pump, capable of drawing 600Pa absolute pressure vacuum.
Best results are obtained with a vacuum down to 100 Pa. To get down to this level at normal temperatures, i.e.
INSTALLATION - TRANSPORT - HANDLING

Other manuals for Lennox MCC Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lennox MCC Series and is the answer not in the manual?

Lennox MCC Series Specifications

General IconGeneral
BrandLennox
ModelMCC Series
CategoryChiller
LanguageEnglish

Related product manuals