Luffing Jib Raising Procedure
Luffing Jib No. 59 on Boom No. 58 HL
EN 13000
16000 SERIES 2
Maximum Boom and Luffing Jib Lengths Lifted Unassisted Using Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 59
Boom to
Luffing Jib
Angle Luffing Jib No. 59
Boom to
Luffing Jib
Angle
Feet Meters Feet Meters Degrees Feet Meters Degrees
98.4 30,0 78.7 - 157.5 24,0 - 48,0 145 78.7 - 118.1 24,0 - 36,0 145
177.2 - 275.6 54,0 - 84,0 90 137.8 - 236.2 42,0 - 72,0 90
255.9 - 275.6 78,0 - 84,0 70
118.1 36,0 78.7 - 118.1 24,0 - 36,0 145 78.7 24,0 145
137.8 - 236.5 42,0 - 72,0 90 98.4 - 196.9 30,0 - 60,0 90
255.9 - 275.6 78,0 - 84,0 70 216.5 - 275.6 66,0 - 84,0 70
137.8 42,0 78.7 24,0 145
98.4 - 196.9 30,0 - 60,0 90 78.7 - 157.5 24,0 - 48,0 90
216.5 - 275.6 66,0 - 84,0 70 177.2 - 275.6 54,0 - 84,0 70
157.5 48,0 78.7 - 137.8 24,0 - 42,0 90
157.5 - 275.6 48,0 - 84,0 70 78.7 - 137.8 24,0 - 42,0 70
*177.2 *54,0
78.7 - 137.8 24,0 - 42,0 90
——
157.5 - 196.9 48,0 - 60,0 70
Load blocks, hook and weight ball on ground until boom and luffing jib are erected. Boom lengths shown with
an asterisk (*) require lower boom point to be removed.
16000 SERIES 3
Maximum Boom and Luffing Jib Lengths Lifted Unassisted Using Jack-Knife Method
Boom
Length
Over End of Blocked Crawlers Over Side of Crawlers
Luffing Jib No. 59
Boom to
Luffing Jib
Angle Luffing Jib No. 59
Boom to
Luffing Jib
Angle
Feet Meters Feet Meters Degrees Feet Meters Degrees
98.4 30,0 78.7 - 196.9 24,0 - 60,0 145 78.7 - 157.5 24,0 - 48,0 145
216.5 - 275.6 66,0 - 84,0 90 177.2 - 275.6 54,0 - 84,0 90
118.1 36,0 78.7 - 157.5 24,0 - 48,0 145 78.7 - 118.1 24,0 - 36,0 145
177.2 - 275.6 54,0 - 84,0 90 137.8 - 236.5 42,0 - 72,0 90
255.9 - 275.6 78,0 - 84,0 70
137.8 42,0 78.7 - 118.1 24,0 - 36,0 145 78.7 24,0 145
137.8 - 255.9 42,0 - 78,0 90 98.4 - 196.9 30,0 - 60,0 90
275.6 84,0 70 216.5 - 275.6 66,0 - 84,0 70
157.5 48,0 78.7 24,0 145
98.4 - 216.5 30,0 - 66,0 90 78.7 - 137.8 24,0 - 42,0 90
236.2 - 275.6 72,0 - 84,0 70 157.5 - 255.9
48,0 - 78,0 70
*177.2 *54,0
78.7 24,0 145
98.4 - 216.5 30,0 - 66,0 90 78.7 - 137.8
24,0 - 42,0 90
236.5 - 275.6 72,0 - 84,0 70 157.5 - 196.9
48,0 - 60,0 70
*196.9 *60,0
78.7 - 98.4 24,0 - 30,0 90
——
118.1 - 177.2 36,0 - 54,0 70
Load blocks, hook and weight ball on ground until boom and luffing jib are erected. Boom lengths shown
with an asterisk (*) require lower boom point to be removed.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc 16000 Series 2 and is the answer not in the manual?

Manitowoc 16000 Series 2 Specifications

General IconGeneral
BrandManitowoc
Model16000 Series 2
CategoryConstruction Equipment
LanguageEnglish

Related product manuals