AUX DC Inverter Free Match 50HZ R32
◇ Tighten the bolt and ensure that four hooks are in close contact with the nuts and washers,
and the
unit is suspended firmly and reliably onto the hooks.
◇ After the unit is installed ensure it is secure and does not shake or sway.
5.3 Drainage pipe
The drainage pipe should be properly insulated to prevent the generation of condensation.
Heat insulation material: the thickness of rubber insulation pipe should be more than 8mm
◇Drainage pipe must have a downward gradient (1 / 50 1 / 100).T avoid water backflow or
leakage etc.
◇When finish installation please carry out the drainage test to ensure that the water flow