7.1.5 Restore to normal operation after “total off”
NOTE !
Make sure about UPS status with “total off” activate, & Q1 closed, Q2 open and the
battery breaker Q3 in ON in battery cabinet.
View of the panel after pressing the button “total off”:
• All Contactors are open.
• Booster, inverter and Static-Switch shutdown.
LP 33 60kVA
APPLICAT. SUPPLY OFF
= 0%
1. Reset “total off”.
Restore the command “total off” by entering the screen:
MENU/RESET TOTAL OFF
LED TEST
RESET TOTAL OFF *
The load is supplied by the mains through the automatic
bypass.
The booster starts automatically.
The LCD screen must display the status:
APPLICATION ON BYPASS