Material Description Quantity
Output
terminal
of the
power
distributi
on box
Power
output
cable
Power Cable,450/750V,H07Z-
K UL3386,16mm^2,blue,Low
Smoke Zero Halogen Cable
(per meter)
12
Power Cable,450/750V,H07Z-
K
UL3386,16mm^2,Black,Low
Smoke Zero Halogen Cable
(per meter)
12
Power
distribution
box
terminal
Naked Crimping
Terminal,JG2,16mm^2,M6,95
A,Tin Plated,for OEM
48
Groundin
g cable of
the
equipmen
t room
Cable Wire,450/750V,60227 IEC
02(RV)50mm^2,yellow green,
170A(per meter)
1
Terminal Naked Crimping Terminal,JG,
50mm^2,M10,Tin Plating
1
Groundin
g cable of
the
cabinet
Cable Power Cable,450/750V,H07Z-
K UL3386,25mm^2,Yellow
Green,Low Smoke Zero
Halogen Cable(per meter)
1
Terminal 1 Naked Crimping
Terminal,JG2,16mm^2,M6,95
A,Tin Plated,for OEM
1
Terminal 2 Naked Crimping Terminal,OT,
25mm^2,M8,Tin
Plating,Naked Ring Terminal
1
Operation Procedure
Step 1: Install slide rails.
Install the slide rails 7 U below the top of the power distribution box and align the bottom
planes of slide rails with the corresponding scale line, as shown in (1) and (2) of Figure E-10.
Step 2: Install captive nuts.
Install two captive nuts into the fourth and fifteenth holes from the bottom of the slide rail, as
shown in (3) of Figure E-10.
HUAWEI NetEngine40E Universal Service Router
Hardware Description
E DPD300-4-12 Power Distribution Box, Dual-Two Inputs
Issue 01 (2015-08-30) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
738