18-AC124D1-1A-EN 9
STEP 5 - Replace the pressure tap valve cores
after the service valves have cooled.
STEP 2 - Check for leaks by using a soapy solu-
tion or bubbles at each brazed location.
Remove nitrogren pressure and repair any leaks
before continuing.
Section 8. Refrigerant Line Leak Check
8.1 Check For Leaks
STEP 1 - Pressurize the refrigerant lines and
evaporator coil to 150 PSIG using dry nitrogen.
Section 9. Evacuation
9.1 Evacuate the Refrigerant Lines and Indoor Coil
Important: Do not open the service valves until
the refrigerant lines and indoor coil leak check
and evacuation are complete.
STEP 1 - Evacuate until the micron gauge reads
no higher than 350 microns, then close off the
valve to the vacuum pump.
0350
Microns
ON
OFF