RT-SVX36G-EN 49
Installation
Requirements for Electric Heat Units
All SEHL Units (380 minimum voltage).
Verify that the power supply complies with the electric heater specifications on the unit and
heater nameplate.
Inspect the heater junction box and control panel; tighten any loose connections.
Check electric heat circuits for continuity.
SEHL Units w/200V or 230V Electric Heat: (Requires Separate Power Supply to
Heater)
Connect properly sized and protected power supply wiring for the electric heat from a
dedicated, field- supplied/installed disconnect to terminal block 4TB2, or to an optional unit
mounted disconnect switch 4S15.
Requirements for Gas Heat
Gas supply line properly sized and connected to the unit gas train.
All gas piping joints properly sealed.
Drip leg Installed in the gas piping near the unit.
Gas piping leak checked with a soap solution. If piping connections to the unit are complete,
do not pressurize piping in excess of 0.50 psig or 14 inches w.c. to prevent component failure.
Main supply gas pressure adequate.
Flue Tubes clear of any obstructions.
Factory-supplied flue assembly installed on the unit.
Connect the 3/4” CPVC furnace drain stubout to a proper condensate drain.
Requirements for Hot Water Heat (SLH_)
Route properly sized water piping through the base of the unit into the heating section.
Install the factory-supplied, 3-way modulating valve.
Complete the valve actuator wiring.
Requirements for Steam Heat (SSH_)
Install an automatic air vent at the top of the return water coil header.
Route properly sized steam piping through the base of the unit into the heating section.
Install the factory-supplied, 2-way modulating valve
Complete the valve actuator wiring.
Install 1/2”, 15-degree swing-check vacuum breaker(s) at the top of each coil section. Vent
breaker(s) to the atmosphere or merge with return main at discharge side of steam trap.
Position the steam trap discharge at least 12" below the outlet connection on the coil.
Use float and thermostatic traps in the system, as required by the application.
O/A Pressure Sensor and Tubing Installation (All units with Statitrac or Return Fans)
O/A pressure sensor mounted to the roof bracket.
Factory supplied pneumatic tubing installed between the O/A pressure sensor and the
connector on the vertical support.
Field supplied pneumatic tubing connected to the proper fitting on the space pressure
transducer located in the filter section, and the other end routed to a suitable sensing location
within the controlled space (Statitrac only).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane IntelliPak SXHL Series and is the answer not in the manual?

Trane IntelliPak SXHL Series Specifications

General IconGeneral
BrandTrane
ModelIntelliPak SXHL Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals