4.4 Measuring pipe
In order for the pipes to be laid correctly, the following points
must be observed:
Keep the measuring pipe as short as possible and avoid
sharp bends.
Lay the measuring pipe in such a way that no deposits
can accumulate in it. Gradients should not be less than
approx. 8 % (ascending or descending).
The measuring pipe should be blown through with
compressed air or, better yet, flushed through with the
measuring medium before connection.
Completely depressurize the measuring pipe if the medium
is a fluid.
Lay the measuring pipe in such a way that gas bubbles
(when measuring fluids) or condensate (when measuring
gases) can flow back into the process line.
When measuring steam, lay the measuring pipe in such a
way that hot steam cannot flow back into the process
connection (water trap, e.g., a water trap pipe that is filled
with water before installation).
Check the tightness of the connection.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB 261GS and is the answer not in the manual?

ABB 261GS Specifications

General IconGeneral
BrandABB
Model261GS
CategoryTransmitter
LanguageEnglish

Related product manuals