46/60 Commissioning
Bosch Rexroth AG, A10VO, A10VSO, A10VNO, A10VSNO Series 52 and 53, RE 92703-01-B/04.2018
▶ After the running-in phase, have a hydraulic fluid sample analyzed for the required
cleanliness level.
▶ Change the hydraulic fluid if the required cleanliness level is not reached. If a
laboratory test is not carried out after the running-in phase, it is recommended to
change the hydraulic fluid.
8.3 Recommissioning after standstill
Depending on the installation conditions and ambient conditions, changes may occur
in the hydraulic system which make recommissioning necessary.
The following criteria may make recommissioning necessary:
• Air and/or water in the hydraulic system
• Old hydraulic fluid
• Other contamination
▶ Before recommissioning, proceed as described in chapter8.1 “Initial
commissioning” on page43.