A-5
INSTALLATION
IN GENERAL
Take off the packaging material with care. Take off all the material used for packing and accessories.
If the equipment is delivered with casters, always lock them after installation and use flexible wire. It
must also be installed with restraining device (chain comes with the oven) to guard against
transmission of strain to the gas supply and connectors.
1. To the electrician
Electrical supply installation must be in accordance with the electrical rating on the nameplate.
WARNING
The electrician must make sure that the supply cable does not come in contact
with the oven top which becomes hot.
2. To the plumber
This equipment is to be installed to comply with the applicable federal, state or local plumbing codes.
Connect the steam system (1/4 NPT) to the cold water distribution network.
We highly recommend to use a water softener to eliminate minerals in the water.
We suggest you to use CUNO # CFS6135 (Doyon part number PLF240).
WARNING
Do not adjust the needle valves, it has been done at the factory.
BEARING MAINTENANCE
Every month you must grease the bearing situated at the
bottom of the oven. To lubricate the oven you need to
use the zerk located in the front bottom for the simple
oven and at the center for the double oven .
Use the grease gun located on top of the oven. Only two
squeezes will be sufficient.
WARNING
It is very important to use the same type of grease that the manufacture recommends.
High temperature grease DUPONT GPL227FG
Otherwise the warranty of the unit will be annulled.