Multi Variable Air Conditioners Cassette Type Indoor Unit
12
(3) It’s strongly recommend to do the drain test before ceiling decoration.
watering pot
(the pipe should be about 100mm)
(inject water from air vent)
above 100mm
drainage pipe
Fig 4.3.5
4.4 Panel installation
4.4.1 Notices for installation
(1) Improper decorative panel installation could cause the following problems.
Condensation cause water drop
dew
air leakage
Fig 4.4.1
(2) Ensure that its clearance-free between decoration panel and ceiling board after installation, if
not, please adjust the body position.
There can't be gap
Fig 4.4.2
(3) Connect the decoration panel terminals (Female) to body terminals (male) as shown in gure
4.4.3.
indoor unit side
panel side
Fig 4.4.3