10 PNEG-634 2000 Top Dry Fan/Heater
3. Installation
Fan/Heater Mounting
1. Inspect the fan platform for proper installation per instructions in the Top Dry erection manual.
2. Raise the Top Dry Fan/Heater units to the platform. Use the Table below to determine the height of
the platform from the base of the Top Dry unit.
3. Mount the Top Dry Fan/Heater units to the bin entrance sheets. Fan legs should set on the platform.
Top Dry Bin Eave Height
Control Box Mounting
1. Mount control boxes at eye level, regardless of whether using the manual control center of the econo
control center. Makesure to have the control boxes mounted so that the fan and heater unit(s) are
in view.
2. Keep in mind that wire will be used to interconnect the control center with the fan and heater unit(s).
3. Use the hole pattern in Figure 3C on Page 11 to drill holes for mounting the control box.
Figure 3A 2 Fan Top Dry Configuration
# of Rings Eave Height
5 18'-5"
622'-1"
7 25'-9"
829'-5"
9 33'-1"
10 36'-9"
11 40'-5"