2 |
Once a flame is established, the gas pressure must not fall more than another 3"WC as
the unit reaches the maximum firing rate.
Commissioning a boiler
For the commissioning of each boiler:
1. Record the type of gas and incoming gas pressure.
Type of Gas _________ Gas Pressure _______ Ignition Gas Pressure _______Lock-up
Gas Pressure _________ Static Gas Pressure______High Fire Gas Pressure________Low Fire
Original CO
2
%________High Fire Adjusted CO
2
________High Fire Original CO
2
%_______Low Fire
Adjusted CO
2
________Low Fire µA _________High Fire µA ________Low Fire
If your system is comprised of multiple boilers, after commissioning the individual boilers:
Verify the gas pressure provided to the system.
Operate all the boilers at their maximum firing rate, and achieve a steady state.
Record the lowest gas pressure observed _________ .
High fire all boilers ( pressure should not deviate significantly from the individual pressure recorded
earlier).
You will use the V-10 controller's "Manual" mode to perform the following boiler setup. Once
commissioning is completed, you must return the load to the desired load configuration. If this is a
multiple-boiler system, disconnect the boiler network wiring by removing the terminal block TB2 pins 1-10
(unplug the 12-pin connector).
2. Set the Load Type to Manual as well as the maximum supply and the heat output values.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBC SL G3 Series and is the answer not in the manual?

IBC SL G3 Series Specifications

General IconGeneral
BrandIBC
ModelSL G3 Series
CategoryBoiler
LanguageEnglish

Related product manuals