v Attach cables serially between enclosures; do not skip an enclosure.
v The last enclosure in a chain must not have cables in port 2 of canister 1 and
port 2 of canister 2.
v Ensure that cables are installed in an orderly way to reduce the risk of cable
damage when replaceable units are removed or inserted.
Connecting Ethernet cables to node canisters
The control enclosure has several Ethernet ports present or optionally present on
the rear of each node canister. Ports 1 and 2 provide access to system management
facilities. Ports 1, 2 and 3 on the rear of each canister can also provide iSCSI
connectivity.
Procedure
To install the cables, complete the following steps.
1. Connect Ethernet port 1 of each node canister in the system to the IP network
that will provide connection to the system management interfaces, as shown in
Figure 23 on page 25. This port can also be used for iSCSI connectivity to the
fab10007
4
5
6
7
8
9
1
2
3
*
Figure 22. Connecting the SAS cables
24 Storwize V7000 Gen2: Quick Installation Guide

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM Storwize V7000 Gen2 and is the answer not in the manual?

IBM Storwize V7000 Gen2 Specifications

General IconGeneral
BrandIBM
ModelStorwize V7000 Gen2
CategoryStorage
LanguageEnglish

Related product manuals