SERVICING
Ideal Logic Combi - Installation and Servicing
36
SERVICING SCHEDULE
For the very latest copy of literature for specication & maintenance practices, visit our website www.idealboilers.com, where you
will be able to download the relevant information. N.B. Technical Bulletins are also available on www.idealboilers.com.
WARNING. Always turn OFF the gas supply at the gas service cock, and switch OFF and disconnect the electricity
supply to the appliance before servicing.
Combustion testing must be carried out by a competent person using a combustion analyser conforming to BS7927.
To ensure the continued safe and efcient operation of the appliance it is recommended that it is checked at regular intervals and
serviced as necessary. The frequency of servicing will depend upon the installation condition and usage but should be carried out
at least annually.
It is the law that any service work must be carried out by a Gas Safe Registered Engineer. In IE service work must be carried out
by a Registered Gas Installer (RGII).
INSPECTION
1. Light the boiler and carry out a pre-service check, noting any
operational faults.
2. Check the ue terminal (and terminal guard if tted) is
undamaged and clear of any obstruction.
3. Check all water and gas joints for signs of leakage. Remake
any suspect joints ensuring a gas tightness check is carried
out if applicable and the water system is correctly relled,
vented and re-pressurised.
CLEANING PROCEDURE
Note. In order to carry out either servicing or replacement of
components the boiler front panel must be removed.
Refer to Frame 37.
1. Clean the main burner. Refer to Frame 39.
2. Clean the heat exchanger & condensate trap/siphon. Refer to
Frames 40 & 41.
3. Check the main injector for blockage or damage. Refer to
Frame 45.
4. Check that the ue terminal is unobstructed and that the ue
system is sealed correctly.
ALSO IF THE DHW FLOW RATE IS IN QUESTION :-
5. Check the DHW lter for blockage. Refer to Frame 66.
The cleaning procedures are covered more fully in Frames 38-42
and MUST be carried out in sequence.
IMPORTANT.
6. After completing the servicing or exchange of components
always test for gas tightness.
7. When work is complete the front panel MUST be correctly
retted, ensuring that a good seal is made.
Do NOT OPERATE the boiler if the front panel is

8. If, for any reason, the condensate trap/siphon has been
removed ensure the trap is relled with water before
reassembling.
9. Check the gas consumption.
10. Check combustion by connecting the ue gas analyser to the
ue gas sampling point as shown in the diagram and measure
CO & CO
2
.
If the CO/CO
2
ratio is greater than 0.004 AND the integrity of
the complete ue system and combustion circuit seals have
been veried and the inlet gas pressure (and gas rate) have
been veried, then contact Ideal.
11. Complete the service section in the Benchmark
Commissioning Checklist.
Flue Sampling Point
Air Sample
Point
Ensure all caps and seals
are re-fitted after use
GENERAL
Please Note: During routine servicing, and after any
maintenance or change of part of the combustion
circuit, the following must be checked:
- The integrity of the ue system and the ue seals,
- The integrity of the boiler combustion circuit and
the relevant seals
- The operational (working) gas inlet pressure at
maximum rate.
- The gas rate
- The combustion performance.
COMPETENCE TO CARRY OUT THE CHECK
OF COMBUSTION PERFORMANCE
Please Note: BS 6798:2009 Specication for
installation and maintenance of gas-red boilers of
rated input not exceeding 70kW net advises that:
- The person carrying out a combustion
measurement should have been assessed as
competent in the use of a ue gas analyser and the
interpretation of the results.
- The ue gas analyser used should be one meeting
the requirements of BS7927 or BS-EN50379-3
and be calibrated in accordance with the analyser
manufacturers requirements, and
- Competence can be demonstrated by satisfactory
completion of the CPA1 ACS assessment, which
covers the use of electronic portable combustion
gas analysers in accordance with BS7967, Parts 1
to 4.
SERVICING

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL Logic Combi 35 and is the answer not in the manual?

IDEAL Logic Combi 35 Specifications

General IconGeneral
BrandIDEAL
ModelLogic Combi 35
CategoryBoiler
LanguageEnglish

Related product manuals