Operation
Storage of the Machine
157 157
9811/9950-1
4 Fill the fuel tank to prevent a build up of condensation
in the tank.
5 Examine the coolant condition. Replace if necessary.
6 Examine all fluid levels. Top up if necessary.
Put the Machine into Storage
T2-077
1 Park the machine on level, solid ground.
Park the machine in a position where the machine is
easy to get access (in case the machine does not
start at the end of the storage period).
Place suitable timbers under the machine to eliminate
direct contact with the ground.
2 Retract all rams and lower the attachments to the
ground.
3 Vent the hydraulic system.
4 Remove the starter key.
5 Apply a thin layer of grease or petroleum jelly to all
exposed ram piston rods.
6 Remove the battery. Charge the battery.
Keep the battery in warm, dry conditions. Charge the
battery periodically.
7 If you keep the machine outdoors, cover the machine
with tarpaulins or plastic sheets.
During Storage
T2-078
Operate the machine functions each week to prevent a
build up of rust in the engine and hydraulic circuits, and to
minimise deterioration of the hydraulic seals.
HE Services

Table of Contents

Other manuals for jcb 8030 ZTS

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the jcb 8030 ZTS and is the answer not in the manual?

jcb 8030 ZTS Specifications

General IconGeneral
Brandjcb
Model8030 ZTS
CategoryExcavators
LanguageEnglish

Related product manuals