168 Part Number: 000015431 Rev01 5/19
RECOVERY/EVACUATION PROCEDURES
1. Press the power button to stop the ice machine
and disconnect all power to the ice machine and
condensing unit.
2. Install manifold gauges, charging scale, and recovery
unit or two-stage vacuum pump.
3. Open high and low side on the manifold gauge set.
4. Perform recovery or evacuation:
A. Recovery: Operate the recovery unit as directed
by the manufacturers instructions.
B. Pressure test the system.
C. Evacuation prior to recharging: Evacuate to 500
microns. Then allow the pump to run for an
additional hour.
5. Refer to Charging Procedures.

Table of Contents

Other manuals for Manitowoc CVDF1400

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc CVDF1400 and is the answer not in the manual?

Manitowoc CVDF1400 Specifications

General IconGeneral
BrandManitowoc
ModelCVDF1400
CategoryIce Maker
LanguageEnglish

Related product manuals