INSTRUCTIONS PL600H/PL1000H
9
B
A
Figure 17
Figure 19
Figure 20
Figure 18
3.3.1 Installation of the Gearmotor
3.3.1.1 Installing on Gates without Rack
The PL600H/PL1000H can be installed in two situations:
1). Installing on gates without rack; in this condition must be installed first, followed by PRK-1 rack.
2). Installing on a gate with rack; in this condition must be connected to the existing rack.
1). Dig the foundations based on “Preparation for Motor Installation” and please notice the distances indicated in
Figure 12.
2). Lay the conduits for the power cables and leave 30-50 cm longer as Figure 17.
3). Fit the two bent bins (as below part in Figure 18) into the foundation and fix them above and below with two
nuts (as below part in Figure 18); make sure the outstanding part does not exceed the maximum height as
Figure 18.
4). Put the foundation plate and make sure the gate keeping the distances shown as Figure 12.
5). Fit the conduits through the hole of the foundation plate.
6). Pour the concrete.
7). Sink the plate into the concrete and make sure it is parallel to the leaf.
8). After the concrete is dry enough, remove the two upper nuts form the plate and cut the cable conduits above the
plate if the conduits are too long.
9). Remove the two caps beside the left and right sides of the gearmotor as shown in Figure 19.
10). Put gearmotor on the plate and then screw the two nuts and washers as Figure 20.
A
B
25~35mm