EasyManuals Logo
Home>Reflex>Water System>Fillcontrol

Reflex Fillcontrol User Manual

Reflex Fillcontrol
16 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #8 background imageLoading...
Page #8 background image
8
System inställningar/
System-dependent setting
p
SV
[bar] =
Säkerhets upphämtning av trycket i värme generatorn/
Safety pick-up pressure at the heat generator
p
max
[bar] = 0.3 bar
0.5 bar
p
e
[bar] =
Slutnings tryck av expansionkärl/
Final pressure of the expansion vessel
p
a
=
vatten tillförsel när trycket understiger det önskade värdet/
Water make-up when pressure remains under below the required value
p
a
[bar] =
Fyllnings tryck p
F
av expansionskärlet/
Starting or lling pressure p
F
of the expansion vessel
p
0
[bar] = p
statisk/static
+ p
Avdunstning/evaporation
+ 0.2 bar (rekomenderas/recommended) 0.3 bar
p
st
[bar] =
Statiskt tryck (statisk höjd [m] / 10)/
static pressure (static height [m] / 10)
0...0.2 bar
Exempel:
Värmesystemet,
statisk höjd 10 m
(p
st
= 1.0 bar),
p
0
= 1.0 bar + 0 bar + 0.2 bar
(rekomenderas)
p
0
= 1.2 bar
Vid igång körning
Example:
Heating system,
static height 10 m
(p
st
= 1.0 bar),
p
0
= 1.0 bar + 0 bar + 0.2 bar
(recommended)
p
0
= 1.2 bar On-site setting
påfyllningsstation
= p
0
+ 0.1 bar = 1.3 bar
påfyllningsstation AV
= p
0
+ 0.3 bar = 1.5 bar
Förutsättningar för igångkörning/
Prerequisites for initial start-up
Installationen av Reflex påfyllningsstation är nu klar.
Inkopplingen på vattensidan av systemet inkl. uppströms och nedströms avstängningsventiler
sitter på plats.
Elkopplingen enligt bestämmelserna VDE och EVU har blivit utförda.
Rörledningarna till Reflex påfyllningsstation måste sköljas och rensas från smuts och svetsrester.
Kopplingen av avtappningen till avloppet ska följa bestämmelserna enligt DIN EN 12056
Manometern har blivit installerad på reduceringsventilen. (fabriks monterad från approx 06/06)
• Installation reflex ’fillcontrol’ is completed.
• The connection on the water side of the system and to the refill water incl. upstream and downstream shut-off
valves on-site is made.
• The electrical connection acc. to the valid VDE and the local EVU regulations has been established.
• The pipelines towards reflex ’fillcontrol’ have to be rinsed and to be cleaned from dirt and welding residue.
• The connection of the tundish to the sewage has to be made acc. to the valid norm DIN EN 12056.
• The enclosed manometer has been installed at the pressure reducer (from approx. 06/06 factory-mounted).
S
GB
S
Förberedelser igångkörning/
Steps to intial start-up
Vattenkoppling
Öppna alla avstängningsventiler för att ställa in kontroll parametrarna.
Parametrarna skall vara inställda efter kundens behov
Kontroll enheten inkluderar tre nivåer, och lösenord för att skydda service menyn (→ S. 11),
Meny för fyllning av systemet (→ S.10), och kundens inställda meny. Igångkörningen kan kräva vissa
justeringar av de fabriksinställda värdena beroende på vilket system den installeras i.
Establish water connection
Open all upstream and downstream shut-off valves prior to setting the control parameters.
System-dependent parameter setting of the customer menu
The control unit includes three control levels, the password protected service menu ( p. 11), the menu for the
initial filling of the system ( p.10), and the customer menu.
The initial start-up possibly requires the adjustment of some factory settings to the respective system-specific con-
ditions.
GB
reflex påfyllningsstation
Förberedelse igångkörning/Initial start-up

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Reflex Fillcontrol and is the answer not in the manual?

Reflex Fillcontrol Specifications

General IconGeneral
BrandReflex
ModelFillcontrol
CategoryWater System
LanguageEnglish

Related product manuals