The OSMAC RDR Satellite Controller is designed for installation on a substantial concrete foundation with imbedded
conduit of various diameters to enable power, field and earth ground wiring to be routed into the cabinet for connection.
A mounting bolt positioner and basic mounting hardware components are included with each controller. Additional materials
required to complete the installation must be obtained separately. A material list can be compiled by reading through the
instructions completely prior to starting the installation.
CAUTION: For your protection and the safety of the product user, comply with all Caution and Warning
statements within this document. All installation practices must comply with all applicable national and/or local
electrical and construction codes.
Foundation Construction
1. Prepare a hole for the foundation and
wiring conduit using the minimum
recommended dimensions shown in
Figure 1.
Note: Refer to local electrical codes for
required depth of buried wiring.
2. Trench to the foundation site as
required for each wiring run.
3. Position straight and sweep elbow
conduit sections in foundation hole as
shown. Tape the conduit ends to seal
out dirt. Backfill soil to form a 6"
(15.2cm) foundation depth. Conduit
should not extend more than 2" (51mm)
above the finished top surface of the
foundation.
4. Prepare the sides of the foundation hole
with wood forms.
5. Prepare the mounting bolt positioner
with the 5/16 x 4-1/2" bolts and nuts
(provided) as shown in Figure 1. The
threads should extend 2" (51mm) from
the top surface of the bolt positioner.
6. Pour concrete into the formed
foundation hole. Press the mounting
bolt positioner into the concrete until it is
flush and level with the foundation
surface
and aligned with the conduit.
7. Finish the concrete with a level flat area
of 16" x 16" (41cm x 41cm) for the
pedestal base. To prevent pooling at the
base of the pedestal, add a slight taper
away from the cabinet base contact
area. Allow concrete to sufficiently
harden before continuing.
8. Remove the hex nuts from the mounting
studs. Remove the cabinet cover and
doors. Carefully position the controller
onto the studs. Install a flat washer and
a hex nut on each stud and tighten
securely.
6" (15.2cm)
2" (51mm) Max.
2"
(51mm)
Wood Form
Mounting Bolt
Positioner
Mounting Bolt Positioner
See *Note
Plastic Cabinet Base Area
Taper
30"
(76cm)
30"
(76cm)
FRONT
Figure 1
(Conduit Recommendations)
2" (51mm) – Field
(24 Stations Each)
3/4" (19mm) – Power
3/4" (19mm) – Earth Ground
Toro OSMAC
®
RDR Field Satellite
Electric Actuation Models
Installation Instructions
RELEASED Version ©Toro 2006-2006

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Toro OSMAC RDR Satellite Controller and is the answer not in the manual?

Toro OSMAC RDR Satellite Controller Specifications

General IconGeneral
BrandToro
ModelOSMAC RDR Satellite Controller
CategoryController
LanguageEnglish

Related product manuals