Replacement of Cover Gasket for Padmount Switchgear Side-Hinge-2 Models
FIELD SERVICE INSTRUCTIONS MN285009EN April 2019
15.4 Reconnect all control cable connectors and braided
ground leads (Figure 76).
Figure 76.
15.5 Reinstall the base clips fastening the cabinet to the
concrete pad (Figure 77).
Figure 77.
15.6 Repeat step 15.1 through step 15.5 to reinstall the
cabinet on the opposite side of the unit.
16. Repeat the Switchgear Apparatus
Functional Test
16.1 Repeat the Switchgear Apparatus Functional Test as
directed in step 2 on page 4.
ote:N Consult factory service if the apparatus does
not perform as expected during the functional
test.

Other manuals for Eaton GridAdvisor Series II

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Eaton GridAdvisor Series II and is the answer not in the manual?

Eaton GridAdvisor Series II Specifications

General IconGeneral
BrandEaton
ModelGridAdvisor Series II
CategoryCables and connectors
LanguageEnglish

Related product manuals