If additional refrigerant is required
When the piping is longer than pre-charge length, additional charging is necessary.
1. Remove the charging cap from the liquid pipe.
2. Attach a charging pipe hose to the refrigerant cylinder, and connect it to the charging port.
3. Add refrigerant by calculating the additional refrigerant volume in accordance with the table be-
low.
4. Remove the charging hose and install the charging cap.
5. Remove the body caps (gas pipe and liquid pipe), and open the valves.
6. Close the body caps.
NOTES:
Tighten the body caps and charging caps to the torques values specified in the following
table.
Blank cap (mm [in]) Tightening torque (N•m [kgf•cm])
6.35 (1/4) 20 to 25 (200 to 250)
9.52 (3/8) 20 to 25 (200 to 250)
12.70 (1/2) 28 to 32 (280 to 320)
15.88 (5/8) 30 to 35 (300 to 350)
19.05 (3/4) 35 to 40 (350 to 400)
To open and close the valves,
Use an M5 hexagon wrench for liquid pipes.
Use an M10 hexagon wrench for gas pipes.
Pre-charge length
Piping length (L1) pre-charge (m)
30
- 98 -
2-5. Additional charge calculation 2. Pipe design
SYSTEM
DESIGN
SYSTEM
DESIGN

Table of Contents

Other manuals for Fujitsu ARXG24KMLA

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu ARXG24KMLA and is the answer not in the manual?

Fujitsu ARXG24KMLA Specifications

General IconGeneral
BrandFujitsu
ModelARXG24KMLA
CategoryAir Conditioner
LanguageEnglish

Related product manuals