EasyManuals Logo

GE Digital Energy SitePro 10 kVA User Manual

GE Digital Energy SitePro 10 kVA
99 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #24 background imageLoading...
Page #24 background image
Modifications reserved Page 24/99
OPM_SPE_XXX_10K_40K_8GB_V020.doc Operating Manual SitePro 10-15-20-30-40 kVA / S8
The UPS cabinet is free standing and normally does not require bolting to the floor.
In any case the cabinet basement is suitable to be floor fixed, when requested by local standards.
In case of Parallel System, try to place
the UPS modules in sequence of their
numbers (marked on the packing),
because of different setting
depending on their position in the
Parallel System.
If the units are positioned “side by
side”, the side panels must be
mounted on all UPS units.
Remove the side air inlet grids on the
intermediate units to run the control
bus cable connections.
S
P
_
0
1
0
-
0
4
0
_
S
8
_
U
P
S
d
i
s
p
o
s
i
t
i
o
n
_
G
E
_
0
1
5
0
0
m
m
/
2
0
"
M
i
n
.
UPS
3-4-5-6-7-8
Fig. 5.4.1-2 RPA system disposition
5.4.2 Battery location
Batteries require a well-ventilated room with controlled temperature to obtain reliable operation.
The Battery can be install immediately adjacent to the UPS (left or right side) or remotely from the UPS.
If the Battery is installed remotely from the UPS, a wall mounted DC disconnect device must be installed
within line-of-site to both the UPS and the Battery.
The optimal room temperature for the Battery is 20°C (68°F) to 25°C (77°F).
The life of valve-regulated batteries will be reduced by 50% for each additional 10°C (18°F) that the
Battery ambient temperature is above 25°C (77°F).
The Battery System associated with larger UPS is usually either rack mounted or installed in multiple
Battery Cabinets.
Installation and assembly must be made according to the local standards and Battery System
manufacturer‘s recommendations.
The Battery Circuit Breaker or Battery Fuse Box must be mounted as near as possible to the Battery.
WARNING !
Battery installation and connection must be performed by QUALIFIED PERSONNEL
ONLY.
Read all safety instructions before proceeding with the installation (see Section 1).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Digital Energy SitePro 10 kVA and is the answer not in the manual?

GE Digital Energy SitePro 10 kVA Specifications

General IconGeneral
BrandGE
ModelDigital Energy SitePro 10 kVA
CategoryUPS
LanguageEnglish

Related product manuals