41
Combi V3, Combi Max and Vortex Combi models
8 - COMMISSIONING
Refer to Fig. 25 or 25a for boiler controls
Fig. 25a Boiler controls (Vortex Combi 36 shown)
Fig. 25 - Combi V3 and Combi Max boiler Controls
It is important that the following commissioning
procedure is carried out to ensure safe and efficient
operation of the boiler.
Note: Check that the baffles are in position and
that the cleaning cover is correctly fitted and a
good seal made.
1 Check that the water system has been vented and
pressurised, and there are no leaks.
2 Check that all fuel line valves are open.
3 Remove the plastic burner cover (two screws) if it
was not previously removed.