7.2.2.6.2 Hoisting Optical Fibers onto a Tower
This section describes the procedure for hoisting optical fibers onto a tower and the precautions that
must be taken.
Context
Cabling requirements for power cables are met. For details, see Cabling Requirements.
Procedure
1. Hoist the optical fibers onto the tower, as shown in Figure 1.
Figure 1 Hoisting optical fibers onto the tower
(1) Lifting sling
(2) Fixed pulley
(3) optical fibers
(4) Traction sling
NOTICE:
Before hoisting optical fibers onto the tower, connect the optical fibers to the RRU or BBU
based on the labels on both ends of the cables and determine the hoisting direction.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei RRU5909 and is the answer not in the manual?

Huawei RRU5909 Specifications

General IconGeneral
BrandHuawei
ModelRRU5909
CategoryConference System
LanguageEnglish

Related product manuals