6.0 Boiler operation
Before operating the appliance, there are some important pre-igntion checks that need to be
performed. For more information, see Before operating the boiler on page 65. To understand the
boiler start-up process, see Sequence of Operation on page 103.
6.1 Lighting and shutting down the boiler
Start-up Checklist Check
Followed lighting and shutting down procedure.
□
Tested the ignition safety shutoff function (see Testing the ignition safety shutoff on page
68).
□
Checked the appliance's fuel source, and if necessary, performed a fuel conversion using
the appropriate P-kit.
□
Performed gas pressure test by measuring the inlet gas pressure.
□