4-1
MAINTENANCE
VFC 15-150 - VFC 45-225 MODULATING GAS BOILERS
MAINTENANCE4.0
BOILER MAINTENANCE
4.1.1 General Care
Keepcombustiblematerialsandammableliquidsandvapoursawayfromthe
boiler.
Keep vent terminals clear of obstructions (snow, dirt, etc.).
4.1.2 Inspection
Inspection of the boiler is to be performed annually by a qualied service
technician.
4.1.3 Venting
Check vent terminals for and remove any obstructions (e.g. leaves, dust,
other debris).
Check,andcleanorreplaceintakeairltersorscreensasrequired.
Check for holes or leaks in venting. Replace venting as needed.
Examine for any signs of moisture caused by sweating intake air pipes;
insulate as required.
Ensure proper resealing or reinstallation of venting on each servicing.
4.1.4 Condensate Traps
OpenPVCuniontodrain,watchingformud/debris.Flushandrell.
If condensate neutralization is used, check pH level of condensate discharge.
4.1.5 Burner
•
Remove burner to inspect for extent of fouling. Blow clear using compressed
air. Evaluate the magnitude of clearing required, and establish a reasonable
burner inspection schedule. Some boiler / locations may call for annual
service, others showing clean burners will only need attention every 2 – 5
years.Consideraddingairltrationifburnerrequirescleaningeveryyear.
Inalternateyears,visuallyinspectburnerthroughsightglass.Ensureame
isstableandwithoutexcessiveuttering.Normalamepatternisevenly
distributed over the burner surface.
• If burner is operating improperly, remove and clean or replace. Use a CO2
analyzer to determine proper combustion. CO2 level should be 9.0% (for
natural gas) or 10.2% (propane).
• When re-installing burner, ensure it is inserted so that the seam (that runs
alongthelengthofthemetal-bresurface)isplacedasfarawayfromthe
ignitoraspossible(180°rotationarcaway).Alsoconrmsparkgapis1/8".
Conrmvisuallybyremovingviewport,turninggassupplyOFF,andallowing
the boiler to run through an ignition cycle. Compare the spark length with the
spark rod diameter, which is the same 1/8" (e.g. use the rod as a reference).
4.1
CAUTION
Label all wires prior to
disconnection when servicing
controls. Wiring errors
can cause improper and
dangerous operation.
CAUTION
The owner is responsible for
general care of the boiler.
Improper maintenance of
the boiler may result in a
hazardous condition.
WARNING
Whenever the burner is
removed for inspection or
boiler servicing, the sealing
gaskets must be examined
and replaced if damaged.
Upon re-assembly, an
approved leak test solution
must be applied around the
burner ange sealing area to
ensure there is no leakage of
combustible gas/air premix.
WARNING
Fill trap with water before
boiler is rst red to prevent
exhaust fumes from entering
room. Never operate the
boiler unless the trap is lled
with water.
Failure to comply will result
in severe personal injury or
death.

Other manuals for IBC VFC 15-150

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBC VFC 15-150 and is the answer not in the manual?

IBC VFC 15-150 Specifications

General IconGeneral
BrandIBC
ModelVFC 15-150
CategoryBoiler
LanguageEnglish

Related product manuals