v Hardware devices illustrated in these procedures are only for reference and may not depict the device
you are installing into the rack.
Time and items required
Allow 15 to 30 minutes to complete the installation.
The following items are required to install the device using the Universal Two-Post Rack Kit:
v #2 Phillips torque screwdriver
v 1/4-inch slotted-blade torque screwdriver
Parts list
The following parts are provided with the Universal Two-Post Rack Kit Installation.
1. Front brackets (2)
2. Rear brackets, 3-5 inch post (2)
3. Rear brackets, 5-6 inch post (2)
4. Screw, 8-32 x 5/16-in., panhead Phillips (8)
5. Screw, 8-32 x 5/16-in., flathead Phillips (16)
6. Screw, 6-32 x 1/4-in., panhead Phillips (8)
7. Screw, 10-32 x 5/8-in., panhead Phillips (8)
8. Retainer nut, 10-32 (8)
Ensure that the items listed and illustrated above are included in the kit. Note that not all parts may be
used with certain installations depending on the device type.
Figure 15. Rack kit parts
Mounting the switch 27