TP-6727 10/1126 Section 3 Installation Instructions
Tools Required:
D Multimeter (for measuring voltage and current)
D Frequency meter (may be part of multimeter)
D Torque wrench
D Wrenches
D Screwdrivers
D Socket wrenches or nut drivers
D Pliers
D Safety glasses or goggles
D Drill with bits and hole saw (outdoor installations)
Installer/Customer-Supplied Items:
D One 12-volt battery with a minimum rating of 525 cold
crankingamps(CCA)at0_F
D Gravel or crushed stone (outdoor installations)
D Concrete mounting pad
D Cables and conduit
D Fuel supply line with shutoff valve and pipe sealant
(provided by fuel supplier)
D Carbon monoxide (CO) detector(s)
D Exhaust piping (open units)
Required Accessories for Open Units:
D Silencer: Critical SIEO or engine-mounted
D Flex exhaust
D Radiator duct flange
Available Accessories:
D Air cleaner restriction indicator
D Battery charger
D Battery heater
D Block heater
D Flexible fuel lines
D Oil makeup kit (for 30 kW models)
D Rain cap
D Relay kit, includes common fault and auxiliary run
relays
D Rodent guards
D Skid end caps
3.2 Prepare Site
See Section 1.3 for important factors to consider in
choosing the generator set location.
3.2.1 Indoor Installations, Open Units
Maintain a minimum of 457 mm (18 in.) between the
generator set and any adjacent walls or obstructions to
allow access for maintenance and service. See
Figure 2-1 for a typical open-unit installation. Prepare
an area for mounting the generator set.
1. Clear all combustible materials from the generator
set location.
2. Refer to the applicable dimension drawing in
Section 7 to find the minimum mounting pad
dimensions. Lay a concrete pad, including
mounting bolts and stub-ups for the fuel supply and
electrical conduit as shown.
3. Provide air intake and outlet openings as described
in Section 2.2.
3.2.2 Outdoor Installations, Enclosed
Units
Choose a location that is at least 0.9 m (3 ft.) from any
building or structure and near the incoming gas service.
Allow a minimum of 2.4 m (8 ft.) clearance beyond the
exhaust end of the generator set. Plan the installation so
that the exhaust end of the generator set is not directed
toward the building or any openings where exhaust gas
could be drawn into the building.
1. Obtain a building permit and contact your local
utility companies to mark the locations of
underground pipes and cables.
2. Prepare an area for mounting the generator set.
a. Clear all combustible materials, including
plants and shrubs, building materials, and lawn
furniture, from an area at least 2 .4 m (8 ft.)
beyond the exhaust end of the generator set.
b. Spread a 76-mm (3-in.) thick layer of gravel to
support the concrete mounting pad. For the
mounting pad dimensions, see the
corresponding dimension drawing in Section 7
for weather or sound enclosures.

Other manuals for Kohler 15REYG

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Kohler 15REYG and is the answer not in the manual?

Kohler 15REYG Specifications

General IconGeneral
BrandKohler
Model15REYG
CategoryPortable Generator
LanguageEnglish

Related product manuals