TP-6727 10/1134 Section 3 Installation Instructions
3.8 Operation Tests
Hazardous voltage.
Can cause severe injury or death.
Operate the generator set only when
all guards and electrical enclosures
areinplace.
Moving parts.
WARNING
1. Check the items in the Prestart Checklist in the
generator set Operation Manual, including the oil
and coolant levels.
2. Move the generator set master switch to the RUN
position to start the generator set.
3. Use a digital voltmeter (DVM) to check the output
voltage from the generator set. If voltage
adjustments are required, refer to Section 5.5 for
instructions to use the ADC 2100 voltage
adjustment menu.
4. Perform voltage checks as described in the ATS
Operation and Installation manual. Close the main
circuit breaker on the main distribution panel when
instructed to connect power in the test procedure.
5. Test the system operation as described in the ATS
Operation and Installation manual.
6. Set the exerciser on the transfer switch. Refer to
the instructions in the ATS Operation and
Installation manual.
7. Verify that the generator set master switch is in the
AUTO position.
8. Verify that all guards and enclosures are in place.