10 Indoor Unit
Installation
Preparation of Piping
1. Cut the pipes and the cable.
Use the accessory piping kit or the pipes purchased
locally.
Measure the distance between the indoor and the out-
door unit.
Cut the pipes a little longer than measured distance.
Cut the cable 1.5m longer than the pipe length.
2. Burrs removal
Completely remove all burrs from the cut cross section
of pipe/tube.
Put the end of the copper tube/pipe to downward direc-
tion as you remove burrs in order to avoid to let burrs
drop in the tubing.
3. Flaring work
Carry out flaring work using flaring tool as shown below.
Firmly hold copper tube in a bar(or die) as indicated
dimension in the table above.
4. Check
Compare the flared work with figure below.
If flare is noted to be defective, cut off the flared section
and do flaring work again.
Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following procedure.
Copper
tube
90°
Slanted Uneven Rough
Pipe
Reamer
Point down
Bar
Copper pipe
Clamp handle
Red arrow mark
Cone
Yoke
Handle
Bar
"A"
Inclined
Inside is shining without scratches.
Smooth all round
Even length
all round
Surface
damaged
Cracked Uneven
thickness
= Improper flaring =

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the LG Multi V 2 Series and is the answer not in the manual?

LG Multi V 2 Series Specifications

General IconGeneral
BrandLG
ModelMulti V 2 Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals