Page #13 background image
Transport data
Model 14000
13
Model 14000 Load Out Summary
Weight
Each Item
No. 76 Boom 65 m (213')
Series 2
Quantity on Trailer Load #
Item kg (lb) 1 2 3 4 5 6 7 8 9 10 11 12
Upperworks Structure with
Carbody, Gantry & Mast
39 689
(87,500)
1
Crawler Assembly
17 690
(39,000)
1
Crawler Assembly
17 690
(39,000)
1
9,0 m (29'8") Boom Top
4 536
(10,000)
1
5,5 m (18'6") Boom Butt
2 858
(6,300)
1
Upper Side Counterweight
7 938
(17,500)
1 2 2 2 1
12,0 m (39'5") Boom Insert
2 132
(4,700)
1 1 1 1
5,5 m (18'6") Boom Insert
1 633
(3,600)
1
6,0 m (19'8") Boom Insert
1 678
(3,700)
1
3,0 m (10'0") Boom Insert
771
(1,700)
1
Counterweight Tray
9 707
(21,400)
1
Upper Center Counterweight
2,722
(6,000)
1
Detachable Upper Boom Point
499
(1,100)
1
9,2 m (30'0") #134 Jib and Strut
1,188
(2,620)
1
3,0 m (10'0") #134 Jib Insert
140
(310)
1
6,1 m (20'0") #134 Jib Insert
256
(565)
2
Intermediate Frame
680
(1,500)
1
Lower Carbody Counterweight
12 111
(26,700)
1 1
Load Block - 91 mton (100 USt)
1 814
(4,000)
1
14 mton (15 USt) Weight Ball
2 604
(5,740)
1
Rigging Block and Chain
600
(1,500)
1
Miscellaneous
2 722
(6,000)
1
39 689
(87,500)
18 878
(41,620)
19 023
(41,940)
12 972
(28,600)
18 008
(39,700)
8 008
(39,700)
8 008
(39,700)
13 018
(28,700)
5 533
(12,200)
20 820
(45,900)
17 572
(38,740)
6 668
(14,700)
1 2 3 4 5 6 7 8 9 10 11 12
* Note: Does not include blocking, strapping etc.

Other manuals for Manitowoc 14000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc 14000 and is the answer not in the manual?

Manitowoc 14000 Specifications

General IconGeneral
BrandManitowoc
Model14000
CategoryConstruction Equipment
LanguageEnglish

Related product manuals