Hour Meter (See Fig 17)
Use this meter along with the manual to determine when and what type of service on the unit is needed. The display
will show the word “P25” at the first 25 hours of operation and again at every 100 hours of operation after.
Power Management
Start engine without anything connected to generator.
When engine has stabilized, plug in and turn on first load. It is strongly recommended to plug in devices with the
largest power requirement first and the smallest power requirement last to help prevent overloading the generator.
•
•
• Allow generator power requirement to stabilize (engine and attached devices run evenly) before plugging in
the next load.
Fig 17
Cold Weather Operation
Under humid conditions where temperatures drop to 40ºF (4ºC) the carburetor and/or crankcase breather system may begin
to freeze. To prevent icing take the following steps:
1. Replace any old fuel with clean, fresh fuel.
2. Use synthetic 5W-30 or SAE 5W-30 engine oil. Check oil daily or after every 8 hours of use.
3. Turn fuel valve to the open position.
4. Ensure generator is serviced according to the maintenance schedule under “Maintenance” section of manual.
5. Shelter unit from elements.