27
Testing
After installation of the automatic capacitor
bank and programming of the switching
parameters, the following tests can be
performed depending on load situation.
A. No load or cos
ϕ
= 1 or capacitive load
(set desired cos
ϕ
to 0.95 ind.)
1. Select MAN Mode
2. Add two or more steps by pressing the +
button.
3. Select AUTO Mode
All capacitor steps must be switched off
with the programmed delay time between
each switching operation. If all steps are
not switched off, check the following:
• Has an inductive load been connected?
• Have the correct C/k ratio and/or step
size been programmed? (it is
recommended that the C/k value be set to
a value slightly higher than the calculated
value)
B. Inductive load
1. Set desired cos
ϕ
=1
2. Select AUTO Mode
Capacitor steps will now be automatically
switched on to compensate the inductive
load (the controller will not reset if the
inductive current is lower than the preset
C/k value. In such a case, test according to
A. above).
If all steps are switched on and there is still
a demand for additional steps, then check
the setting of C/k. If it is correct, then the
bank is too small to compensate the cos
ϕ
= 1. Select a lower value for cos
ϕ
.
When one stage repeatedly switches on
and off, it means the C/k is set too low
(unless the load actually fluctuates
periodically with a time period equal to the
switching delay time).
13. Testing and troubleshooting