16
ABB Zenith
ZTSCT / ZBTSCT Operation & Maintenance Manual
Entelli-Switch 250 User Setup - CFG Menu
2008
Turn options ON or OFF via
keypad through the CFG menu
Enter six digit access code
(The factory assigned six-digit access code
is located on the back of the controller)
Figure 11
1
Engine Start Relay (De-Energized)
Network Communications
(Option)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
J2
*
PROG 1
PROG 2
GRD (Input Sink)
NIA OUT
ELEV. PRE. OUT
ALARM OUT
MOTOR DISC. OUT
INHIB.>S1
INHIB.>S2
Input and output availability
subject to factory configuration.
*
1
2
3
4
5
6
7
8
9
10
11
12
13
14
J4
*
+12v (Output Source)
LN OUT
L4 OUT
L3 OUT
L2 OUT
L1 OUT
YN IN
YE IN
TSNL IN
Q2/TSL IN
S12 IN
Lithium Battery
Exerciser Battery
Replacement-K-4100 (BR2032)
Service Life-10 Years
† During normal operation
User Access Code
Default-121212
PRODUCT INFORMATION
www.abb.com
24-Hour Service
(773)299-6600
Entelli-Switch MX250
A2
(-)
A1
(+)
RELAY
14 11 12
Customer
Input
Voltage
COM
J2-3
N.O N.C
To
J2/J4
Inputs
WARNING
1
Controller Inputs must be relay Isolated.
2
Controller Outputs have Limited Source Capacity.
Use only ABB Zenith-specified Output Modules.
11 14
R1
A1
(+)
12
21 24 22
A2
(-)
Output
Contacts
22
R1 Output
R1 Output
Contact Rating: 10A @ 250 VAC or 30 VDC
2
3
4
5
6
2421121411
LS OUT
STE OUT
TMS IN
LS IN
S5 IN
TM

Questions and Answers:

ABB Zenith ZTSCT Series Specifications

General IconGeneral
Poles2, 3, 4
SeriesZTSCT Series
ManufacturerABB
Amperage Range30A to 4000A
VoltageUp to 600 VAC
OperationAutomatic
StandardsUL 1008, CSA C22.2 No. 178
EnclosureNEMA 1, 3R, 4, 12
Transfer TypeOpen or Closed Transition

Summary

Introduction

Safety

Installation

Power Connections

Specifies wire sizes, number of cables, and torque values for terminals.

Engine Start Control Connections

Explains connections for engine start control wires to the microcontroller.

Initial Energization

Step-by-step procedure for initial power-up and verification of the transfer switch system.

Control Connections

Details the wiring and connections for the control panel and microprocessor.

Entelli-Switch 250 Controller

The Microprocessor

Details the components of the microprocessor, including the I/O interface and accessories.

User Setting for Voltage & Frequency

Source 1

Details the adjustable parameters for Source 1, including Under/Over Voltage and Frequency settings.

Source 2

Details the adjustable parameters for Source 2, including Under/Over Voltage and Frequency settings.

Accessory Group Packages

Accessory Definitions

How to Set the System Clock

Set System Clock, time and date

Instructions for setting the system clock, time, and date for the controller's accurate operation.

CDT One Event Timer Exerciser

CDP Clock Exerciser

Entelli-Switch 250 User Setup - CFG Menu

Entelli-Switch 250 User Setup - SET Menu

Entelli-Switch 250 User Setup - System Info

Testing

Test Options

Describes the two test positions: "Auto Position" for full transfer and "Test Position" for PM without load interruption.

ATS Testing

Detailed steps for initiating and performing ATS tests, including load and no-load options.

Open Transition

Explains the sequence of operation during an open transition transfer due to source failure or restoration.

Closed Transition

Details the operation of closed transition transfer switches, including paralleling and synchronization.

Initiating a Closed Transition

Steps to initiate a closed transition test, including engine start and synchronization procedures.

Retransfer with Closed Transition

Describes the process of retransferring to the original source with closed transition, ensuring phase relationship.

Emergency Service Procedure for Extended Parallel Time

ZTSCT Transfer Switch

Steps to safely open the ZTSCT transfer switch after an extended parallel time malfunction.

ZBTSCT Transfer/Bypass Switch

Procedures for removing ZBTSCT switches after shunt trip or for inspection and repair.

Sequence of Operation

Bypass-Isolation Operation

Explains how the bypass-isolation switch allows ATS withdrawal for testing/maintenance without load interruption.

100-400 AMP

Details the automatic, bypass, test, isolate, and reconnect sequences for 100-400 AMP models.

600-1200 AMP

Details the automatic, bypass, test, isolate, and reconnect sequences for 600-1200 AMP models.

1600-4000 AMP

Details the automatic, bypass, test, isolate, and reconnect sequences for 1600-4000 AMP models.

1600-3000 AMP Horizontal Bypass

Details the automatic, bypass, test, isolate, and reconnect sequences for 1600-3000 AMP Horizontal Bypass models.

Controls Power Supply (CPS)

Closed Transition CPS Schematic

Provides the schematic diagram for the Closed Transition Controls Power Supply.

Troubleshooting and Diagnostics

General Troubleshooting

Provides a systematic approach to diagnosing and determining basic faults in the transfer switch.

Maintenance and Testing

Inspection and Cleaning

Instructions for inspecting and cleaning the switch, including contact inspection and barrier checks.

Servicing

Guidelines for replacing worn parts and maintaining the transfer switch's operating mechanism.

Testing

Procedures for manual and electrical testing of the transfer switch operation.

Extensive Customer Service and Support

Product Overview

Describes ABB's commitment to quality and the benefits of their power management systems.

Commitment to the Customer

Outlines ABB's dedication to customer satisfaction and partnership throughout the system lifecycle.

Related product manuals