Installing the Cisco cBR Chassis
Installation Methods
The Cisco cBR-8 router can be either mounted on the rack at the front or in the middle. Also, the router can be either mounted on a
standard 19-inch wide four-post equipment rack unit or a two-post rack unit.
The Cisco cBR-8 router usually ships fully loaded. Due to a fully configured system weighing approximately
430 lbs, components must be removed from the chassis to make the chassis lighter for rack installation.
Remove all power supplies, supervisor cards, line cards, rear PIC cards and fan modules before
rack-mounting to reduce the weight to approximately 117 lbs. For instructions on how to remove the
components, see the monitoring sections.
Note
Make sure you place the cards and modules in an anti-static bag until you install the chassis in the rack.Note
Verifying Rack Dimensions
Before You Begin
Before you install the chassis, measure the space between the vertical mounting flanges (rails) on your equipment rack to verify that
the rack conforms to the measurements shown in the figure below.
Figure 1: Equipment Rack Dimensions
2

Other manuals for Cisco cBR 8

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cisco cBR 8 and is the answer not in the manual?

Cisco cBR 8 Specifications

General IconGeneral
BrandCisco
ModelcBR 8
CategoryNetwork Router
LanguageEnglish

Related product manuals