7 Testing
7.1 Test the turbine meter
7.1.1 Commission the turbine meter
After installation, commission the turbine meter to ensure that the equipment is working
properly.
Procedure
1. Inspect all electrical connections to ensure compliance with electrical codes and
safety regulations.
2. Inspect all flange bolts used to secure the turbine meter in-line to ensure that
correct mounting procedures are followed and that flange connections are leak-
free.
3. Evaluate the system setup to ensure that all components are in the correct
sequence for accurate product measurement: isolation valve, strainer, flow
straightener, turbine meter, downstream section, control valve, etc.
4. Ensure that the supply voltage to the preamplifier is within the 10-30 VDC range.