5. Installation5. Installation
.14. .15.
A
B
3. Strip the ground cable insulation to a suitable length(see Figure 5.7).
Figure 5.7 Suitable length
Important:
4. Insert the stripped wire into the OT terminal crimping area and use the hydraulic
clamp to crimp the terminal to the wire (see Figure 5.8).
B (insulation stripping length) is 2mm~3mm longer than A (OT cable
terminal crimping area) 2mm~3mm.
D
C
Figure 5.8 Strip wire
Important:
After crimping the terminal to the wire, inspect the connection to ensure the
terminal is solidly crimped to the wire.
Grounding screw
5. Remove the screw from the heat sink ground point.
Figure 5.9 Fixed cable
For improving anti-corrosion performance,
after ground cable installed, apply silicone or paint is preferred to protect.
Important:
6. Connect the grounding cable to the grounding point on the heat sink,and tighten the
grounding screw, Torque is 3-4Nm(see figure 5.9).

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ginlong S5 Series and is the answer not in the manual?

Ginlong S5 Series Specifications

General IconGeneral
BrandGinlong
ModelS5 Series
CategoryInverter
LanguageEnglish

Related product manuals