Section 2: Mounting and Wiring
13
RJ45
(FOR INTERNET
CONNECTION)
LTE-I-001-V0
7720P
PROGRAM
CONNECTOR
J1
BATTERY
CONNECTOR
TO ROUTER
Internet Connection
Power Connections and Options
Powering the Communicator
There are three ways to power the communicator (see illustrations below):
Standard Installation – The communicator is powered by the supplied AC plug-in transformer.
ULC Commercial Fire and Burglary Compliant Installation – The communicator must be
powered by the control panel.
Shared Transformer Installation – In this installation the supplied AC plug-in transformer may
be used to power both the communicator and the control panel under the following conditions:
You must use the Honeywell 1361-GT Transformer.
This configuration ONLY applies to the VISTA-15P, VISTA-20P control panels when used
with the LTE-I Communicator.
DO NOT use this configuration with any other control panel.
This configuration has not been evaluated by UL.
For all installations, the control panel ground (GND) must be connected to TB1-4 GND on the
communicator. In addition, if using ECP communication, you must connect the +12VDC AUX
voltage output on the control panel (9.6V-13.8V typical) to TB1-3 on the communicator.
iGSMBR-013-V0
12V AUX
GND
COMMUNICATIONS
MODULE
CONTROL PANEL
GND
ECP (+) VOLTAGE INPUT
2
1
4
3
TB1
TRANSFORMER
AC INPUT 2
AC INPUT 1
J1
BATTERY
Standard