5-2
Infrastructure Requirements
Space
Infrastructure Requirements
Space
These devices may be deeper (longer) than other equipment in your network
due to the added PoE power supplies. Also if RPS units have been added to
the rack or wiring closet, ensure enough space has been planned for all
devices.
Space around the switch and around the other units must be available to allow:
access by service personnel
space for power cords and other wiring
cool air circulation
Racks
PoE switch devices and RPS units may be heavier than other non-PoE switch
devices in your network. Therefore you should rack heavy devices at the
bottom of the rack, followed by lighter devices as you move up the rack. This
will help to keep the rack from tipping over.
Secure racks as specified by your rack’s manufacturer. Ensure your racks are
compliant with any earthquake structural rules and regulations.

Other manuals for HP J8697A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HP J8697A and is the answer not in the manual?

HP J8697A Specifications

General IconGeneral
BrandHP
ModelJ8697A
CategorySwitch
LanguageEnglish

Related product manuals