Chapter 3: Getting Started
Product Service 1-800-522-7658
Re-Configuration Process
Events in which you have to “Re-configure”
Installing or commissioning a GFH for the first time
Replacing a fan board or a complete fan box
Replacing an Electro/Acid Sensor
Replacing a solvent sensor
Replacing a RFID board
Replacing a CPU board
Replacing a complete control module
Sash sensor failure
Hardware Configuration mismatch 9A alarm
Before beginning, you will need to have the following:
Green Fume Hood Settings sheet (example provided on next page)
6ft Ladder
Any tools needed for removal of front panel
Some white out, or a small sticker to mark the round RFID tags that are on
the primary filters only (the primary filters are the lower ones that are in
between the lights & fan box)
Piece of paper and a pen
Maintenance card
The User card that is used to operate the hood you are going to re-configure