EasyManuals Logo
Home>Lenze>Servo Drives>EVS9324-ES

Lenze EVS9324-ES User Manual

Lenze EVS9324-ES
189 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #58 background imageLoading...
Page #58 background image
Commissioning
5-1
BA9300SU EN 2.1
5 Commissioning
5.1 Initial switch-on
Stop!
Prior to initial switch-on of the controller, check the wiring for completeness, short-circuit, and earth
fault:
Power connection:
Supply via terminals L1, L2 and L3 (direct mains connection) or alternatively via terminals
+UG, -UG (DC bus connection, network of drives)
Motor connection:
In-phase connection to the motor (direction of rotation)
Feedback system (resolver, incremental encoder, ...)
Control terminals:
Controller enable: terminal X5/28 (reference potential: X5/39)
Direction of rotation terminal X5/E1 or X5/E2
(reference potential: X5/39)
With external setpoint selection: terminals X6/1, X6/2
(reference potential: X6/7)
Covering the power connections:
Put on cover(s) and fix.
Keep to the switch-on sequence!
Note!
All specifications of the parameterization refer to the application example Speed control in
Chapter 11.2.1.
Use the convenient short set-up menus for the commissioning with the operating module
9371 BB or the PC and the Global Drive Control or LEMOC2 in which the codes for the most
important settings are summarized (see also Chapter 7.1.2).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lenze EVS9324-ES and is the answer not in the manual?

Lenze EVS9324-ES Specifications

General IconGeneral
BrandLenze
ModelEVS9324-ES
CategoryServo Drives
LanguageEnglish

Related product manuals