EasyManuals Logo
Home>Midea>Air Conditioner>Vertu series

Midea Vertu series User Manual

Midea Vertu series
54 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #26 background imageLoading...
Page #26 background image
24
operation of the vacuum pump. Make evacuation for 15 minutes or more and check the compound
meter indicates -76cmHg.
6. Turn the stem of the Hi valve about 45°counterclockwise for 6 or 7seconds after the gas coming
out, then tighten the flare nut again. Make sure the pressure display in the pressure indicator is a
little higher than the atmosphere pressure.
7. Remove the charge hose from the Lo pressure charge hose.
8. Fully open the Hi and Lo packed valve.
9. Securely tighten the cap of the packed valve.
Gas leak check
Soap water method
Apply soap water or a liquid neutral detergent on the indoor unit connections or outdoor unit
connections by a soft brush to check for leakage of the connecting points of the piping. If bubbles
come out, the pipes have leakage.
6.5 Pumping down (Re-installation)
Procedure
1. Confirm that both the 2-way and 3-way valves are set to the opened position.
Remove the valve stem caps and confirm that the valve stems are in the opened position.
Be sure to use a hexagonal wrench to operate the valve stems.
2. Operate the unit for 10 to 15 minutes.
3. Stop operation and wait for 3 minutes, then connect the charge set to the service port of the 3-way

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Midea Vertu series and is the answer not in the manual?

Midea Vertu series Specifications

General IconGeneral
BrandMidea
ModelVertu series
CategoryAir Conditioner
LanguageEnglish

Related product manuals