25
valve.
Connect the charge hose with the push pin to the gas service port.
5. Air purging of the charge hose.
Open the low-pressure valve on the charge set slightly to purge air from the charge hose.
6. Set the 2-way valve to the close position.
7. Operate the air conditioner at the cooling cycle and stop it when the gauge indicates 0.1MPa.
8. Immediately set the 3-way valve to the closed position.
Do this quickly so that the gauge ends up indicating 0.3 to 0.5Mpa.
Disconnect the charge set, and amount the 2-way and 3-way valve’s stem nuts and service port caps.
Use a torque wrench to tighten the service port cap.
Be sure to check for gas leakage.
6.6 Re-air purging (Re-installation)
Procedure:
1. Confirm that both the 2-way and 3-way valves are set to the closed position.
2. Connect the charge set and a charging cylinder to the service port of the 3-way valve.
Leave the valve on the charging cylinder closed.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Midea Vertu series and is the answer not in the manual?

Midea Vertu series Specifications

General IconGeneral
BrandMidea
ModelVertu series
CategoryAir Conditioner
LanguageEnglish

Related product manuals