Inspection of the installation
Current regulations require the heating installation to be inspected before it is commissioned. The inspection must
be carried out by a suitably qualified person. In addition, fill in the page for the installation data in the Operating
Manual.
DateSignatureNotesDescription
Brine (page 16)
Non-return valves
System flushed
System vented
Antifreeze
Level/Expansion vessel
Filterball (particle filter)
Safety valve
Shut off valves
Circulation pumps set
Heating medium (page 18)
Non-return valves
System flushed
System vented
Expansion vessel
Filterball (particle filter)
Safety valve
Shut off valves
Circulation pumps set
Electricity (page 21)
Connections
Main voltage
Phase voltage
Fuses heat pump
Fuses property
Outside sensor
Room sensor
Current sensor
Safety breaker
Earth circuit-breaker
Relay output for emergency mode