OPERATING PROCEDURES
6-5
Model C723
Operating Procedures
6
26. Slide two O-rings into one end of the feed tube. Slide
two O-rings on the other end of the feed tube.
Figure 6-18
27. Slide the small O-ring into the groove of the air
orifice. Do not lubricate the O-ring.
Figure 6-19
Note: Make sure the hole in the air orifice is clean and
is not clogged. If the hole in the air orifice should become
clogged, use soap and hot water to clear the hole. Do
not enlarge the hole in the air orifice.
28. Install the air orifice into the hole in the top of the feed
tube (the end of the feed tube without the small hole
on the side).
Figure 6-20
29. Lay the feed tube (with air orifice installed) and the
agitator (factory-equipped agitator machines only) in
the bottom of the mix hopper for sanitizing.
30. Repeat steps 26 through 29 for the other side of the
machine.
Sanitizing
1. Prepare an approved 100 ppm sanitizing solution
(examples: 2-1/2 gal. [9.5 L] of Kay-5
®
or 2 gal.
[7.6 L] of Stera-Sheen
®
). Use warm water and follow
the manufacturer's specifications.
2. Pour the sanitizing solution over all the parts in the
bottom of the mix hopper and allow it to flow into the
freezing cylinder.
Figure 6-21
Note: You have just sanitized the mix hopper and parts.
Therefore, make sure your hands are clean and
sanitized before proceeding to the next step.
12029